Efficiency and Quality Delivered to Waitara Park Rise

Waitara Park Rise

Have you been following our Waitara Park Rise project?

We have now delivered over 332 of 516 bathroom pods to the site, with the remaining 184 pods set to roll off our production lines in 2 weeks!  This saw Interpod exceed the expectations outlined in the site programme.

Richard Crooks Construction are happy with the performance of the Interpod team not only for our efficiency but also the quality of bathrooms delivered thus far. Interpod’s management of this project has far exceeded the requirements of the original scope and we look forward to ensuring all bathroom pods are delivered and installed on time.