Interpod has been awarded the bathroom pod package for Scape State Library Exchange, one of the most significant buildings to rise in Melbourne’s CBD this decade. Working with head contractor Built, we will manufacture and deliver 1,373 bathroom pods across two pod types for the 58-storey tower.

About Scape State Library Exchange
Scape State Library Exchange rises 58 storeys directly above the new State Library Station, on the corner of Swanston and La Trobe streets. It is Scape’s first over-station development and is set to become the world’s tallest student accommodation tower.
The building is a partnership between Scape by The Living Company and RMIT University, who have committed more than $270 million combined to the project. RMIT will occupy the first nine levels for teaching, research and industry spaces, with student accommodation on the levels above.
For Melbourne, it adds much-needed purpose-built student housing in the heart of the city’s university precinct. Construction is expected to be completed in mid-2029.
Why bathroom pods suit CBD sites
Few Melbourne sites are as complex. The tower sits above the deepest station in the Metro Tunnel, 42 metres below Swanston Street, and beside one of the world’s busiest tram corridors. Space for deliveries, storage and trades is tight, and every day on the program counts.
That is where bathroom pods earn their place. Each Interpod pod is manufactured offsite in a controlled factory environment, then delivered finished, tested and ready to install. Tiling, waterproofing, plumbing, fixtures and finishes are all completed before the pod reaches site.
For Built, that means:
- Fewer trades and less material moving through a constrained site
- Bathrooms taken off the critical path
- Consistent quality across every pod, inspected before it leaves the factory
- A steady, predictable floor-by-floor installation program
With 1,373 pods across just two pod types, the project also benefits from repetition, with standardised designs allowing production to run efficiently at scale.
Project timeline
Design and coordination with Built’s project team is under way, with the first pods scheduled to arrive on site in early 2027.
We thank Built for the continued partnership, and Scape and RMIT for the opportunity to be part of the team delivering one of Melbourne’s landmark buildings.
Planning a project with complex site constraints or a tight program? Talk to our team about how bathroom pods can help.